What is ministerial approval process or streamline permit process?
The ministerial approval process or also called "as of right" permitting is the most favorite permitting process for a home owner or a developer who wants to get the entitlements for their project. This is the fastest way to get plans approved by the city because the review process is streamlined.
In August 2020, the California Supreme Court addressed the circumstances under which a public agency may characterize the issuance of well construction permits as “ministerial,” and hence not subject to the California Environmental Quality Act, versus “discretionary,” in which case CEQA applies.
Under CEQA, ministerial approvals involve little or no discretion, merely applying a checklist or clear requirements to the facts as presented, and are often issued over the counter by county staff. In contrast, discretionary approvals involve judgment or deliberation, allow a county to use discretion to decide whether to issue the approvals and how best to shape or condition those approvals to avoid environmental issues, and are often issued by an appointed or elected decision-making body. CEQA review only applies to discretionary approvals.
What is the difference between Ministerial vs. Discretionary process?
“Ministerial processing” or “ministerial approval” is a streamlined permit process for development approval involving little or no personal judgment by the public official. As opposed to the "Discretionary review process" that allows for public hearings which brings a lot of uncertainty and a months or years-long approval process, Ministerial approval is as short as 90 days. This short and streamlined approval process helped the new SB-9 law, which allows for more units in single-family home-zoned areas, to be realistically possible to apply even in tough neighborhoods.
The framework for the Ministerial approval was originally set by SB 35 and issued to create more affordable housing. This bill requires cities and counties to streamline the review and approval of eligible affordable housing projects through a ministerial approval process, exempting such projects from environmental review under the California Environmental Quality Act (“CEQA”). This process does not allow public hearings to consider the merits of the project; rather, only design review or public oversight of the development is allowed, which must be objective and strictly focused on assessing compliance with criteria required for streamlined projects as well as objective design review of the project.
Depending on the number of housing units proposed in the project, the jurisdiction has only a short timeframe within which to review the application to determine if it is eligible for processing under SB 35 (between 60-90 days). If it is determined that the project is eligible, SB 35 specifies the timeframes within which the jurisdiction has to make a final decision on the application (between 90-180 days).
Now, if you want to make an addition to your house to add one more unit or you want to split your lot to make a new house on that lot, you can choose to take the streamlined Ministerial approval process and get the permits in just 90 days. No need to worry about your neighbor's willingness to let you build. You just have to find out how large a house could be on your lot and your finances.
You could hire an architect to find out the size of the house on (each) lot which is approx. $2,000 or order Development Analysis for your property that starts from $199. In regards to financing your project, many cities in California offer financial support with programs for affordable housing. For instance, San Francisco gives residents significant down payment to purchase a house in the city. Great financing programs and free money are available for California residents who want to build an ADU on the property.
Find out your property’s untapped market value through the ministerial review process.
Get permits fast in Agoura Hills
Get permits fast in Baldwin Park
Get permits fast in Bell Gardens
Get permits fast in Bellflower
Get permits fast in Beverly Hills
Get permits fast in Chula Vista
Get permits fast in Culver City
Get permits fast in Diamond Bar
Get permits fast in El Segundo
Get permits fast in Hawaiian Gardens
Get permits fast in Hermosa Beach
Get permits fast in Hidden Hills
Get permits fast in Huntington Park
Get permits fast in Imperial Beach
Get permits fast in La Canada Flintridge
Get permits fast in La Habra Heights
Get permits fast in Lemon Grove
Get permits fast in Long Beach
Get permits fast in Los Angeles
Get permits fast in Manhattan Beach
Get permits fast in Montebello
Get permits fast in Monterey Park
Get permits fast in National City
Get permits fast in Pico Rivera
Get permits fast in Rancho Palos Verdes
Get permits fast in Redondo Beach
Get permits fast in Rolling Hills
Get permits fast in Rolling Hills Estates
Get permits fast in San Fernando
Get permits fast in San Francisco
Get permits fast in San Gabriel
Get permits fast in San Marcos
Get permits fast in San Marino
Get permits fast in Santa Clarita
Get permits fast in Santa Fe Springs
Get permits fast in Santa Monica
Get permits fast in Sierra Madre
Get permits fast in Signal Hill
Get permits fast in Solana Beach
Get permits fast in South El Monte
Get permits fast in South Gate
Get permits fast in South Pasadena
Get permits fast in Temple City
Get permits fast in Unincorporated Los Angeles County
Get permits fast in Unincorporated San Diego County
Get permits fast in West Covina
Get permits fast in West Hollywood